The Federal Government Tuesday formally reopened the Third Mainland
Bridge barely three months after it was partially closed for intensive
repair works at eight expansion joints on both sides of the longest
bridge in Africa. It is11.8 kilometre-long. Sources said the repair
gulped about N1.5 billion.
Minister of Works, Mike Onolememen, an architect, in his address at
the official reopening of the ever busy bridge noted that the federal
government had kept faith with the promise that the repair works that
commenced on August 10, 2012 would be completed about November 6, 2012,
as it had come to pass.
Onolememen added that not only were the repair works completed about
10 days ahead of schedule, they were also completed at the awarded
contract sum without variation.
He said at the commencement of the repairs on behalf of the federal
government that everything possible would be done to cushion the
frustration and inconveniences that would be caused to road users due to
the partial closure of the bridge, pledging to complete the project
ahead of schedule.
The Minister at Tuesday’s event thanked President Goodluck Jonathan
for his support and sustained funding of the project, just as he
commended Governor Babatunde Fashola of Lagos State “for his wonderful
cooperation and collaboration not just on this project, but on all
federal projects in the state”.
According to the Minister, “the project employed specialised technology which is not readily available in the country.
“The materials utilized, hydro-demolition machine, as well as technical expertise to execute the works were all imported.
“With the completion of the repair works on the three joints on the
Lagos Island bound carriageway and five expansion joints on the
Oworonshoki bound carriageway, the contract for the repair of the Third
Mainland Bridge has been successfully completed. “The works have been
completed before the scheduled date of November 6, 2012”, Onolememen
stated.
The longest bridge linking Lagos Island with the Mainland was
partially closed to traffic on Sunday 8 July, 2012 while repair works
commenced on it on Monday, 9 July, 2012.
Initially, commercial activities were almost paralysed at Idumota and
many other parts of Lagos Island as the closure of the bridge created a
lot of hardship for commuters and motorists traveling from the Mainland
to the Island.
At least 700 officers of the Lagos State Traffic Management
Authority, LASTMA, were deployed to areas close to the bridge to
ameliorate the plight of motorists and commuters.
Lagos State Commissioner for Transportation, Kayode Opeifa, after
yesterday’s re-opening said the repair was completed and the bridge was
ready for use since Sunday.
Speaking further on the project, the Minister explained that the
dynamic investigation report which was completed and submitted to his
ministry indicated that one expansion joint with vertical gaps greater
than 10 mm at Axis 10-11, 13-14, 16-17 and 25-26 along the Lagos bound
carriageway were in very critical state and required immediate repairs,
pointed out that seven joints at Axis 55-56, 57-58 and 64-1along the
Lagos bound carriageway and 13-14, 22-23, 34-35 and 43-44 along
Oworonshoki bound carriageway had vertical gaps between 4-10 mm which on
border line.
He further noted that 16 joints on the inbound and 19 joints on the
outbound carriageways equally required regular cleaning, stressing that
FERMA would be directed to add this to their maintenance programme. He
said joints at Axes 13-14, 19-20, 16-17 and 25-26 were restored in an
earlier contract executed in 2006 by the ministry using the same
contractor.
The minister who stated that traffic diversion plans and programmes
had been implemented with the relevant stakeholders to minimise traffic
congestion and inconveniences to the populace during the period of
partial closure of the bridge from July 6 to October 30, 2012, added
that actual demolition of sections of the bridge deck affected at Axis
64-1 for the restoration of the joints had been completed and
reinstated.